READINESS INDICATORS OF GUARANTEED CAPACITY SOURCES

July, 2020 Year

Day
 
Actual Readiness Days

GUARANTEED CAPACITY SOURCES

Actual Readiness Days

COST OF GUARANTEED CAPACITY (GEL) 

"G-power" LTD Air Turbine TPP 31 Days 1 484 838
"Georgian International Energy Corporation" LTD Energy Unit N:3 Gardabani TPP 0 Days 0
"Georgian International Energy Corporation" LTD Energy Unit N:4 Gardabani TPP 31 Days 850 764
"Mtkvari Energy" LTD Energy Unit N:9 Gardabani TPP 4 Days 309 320